Former MGP - 2004 - SAVANNAH, USA

  • Site : former MGP site

  • Contaminants : coal tar, BTEX, PAH, NAPL, ...

  • Site challenges : stratigraphy 3 zones - deep (15 m) – large DNAPL mass – sensitive structures (utilities – center town)

  • Pilot to evaluate effectiveness of 'Catalyzed Hydrogen Peroxide' injections - CHP

  • Full scale:
       
     1 235 fixed injectors at 4,5-m spacing
         11 300 m3 of 8 % H2O2 injected
          11 months - daily 'real time' monitoring
         Goals were met : No NAPL, PID<50 ppm
         Remediation goals were obtained

  • ISCO remediation cost: $9,5 million

  • Other remediation option cost: excavation estimated at $21 million

 