- Surface : 3 500 m²
- Volume : ≈ 15 000 m³
- Geology : sand and clay
- Pollution : TCE and breakdown products DNPAL - unexpected L-NAPL
- Aquifer : 3 m bgs
- Duration : 6 months
- Performance :
recovered D-NAPL 5 000 Kg recovered L-NAPL 25 000 Kg
- Achieved goals : > 95 % (TCE < 3 mh/Kg)
|
|